Budgeting BESS for FY27-28: What to Put in the Capex Line
Indian buyers set next year's capital budget in the third quarter. For FY27-28 — 1 April 2027 to 31 March 2028 — that work is happening now, and a battery storage line is one of the harder ones to write, because the number has to survive three separate conversations: with a finance team that wants a defensible figure, with a board that wants a contingency basis, and with a project team that wants the asset live on a date.
Those three are not independent. The figure depends on where you draw the scope boundary. The contingency depends on which end of a published band your site actually sits at. And the date depends on a lead time that, if assumed wrong by a few weeks, moves the entire spend into a different financial year.
This post takes them in that order, using our published cost bands as the worked reference.
Start with the scope boundary, not the number
There is no single per-MWh figure for a BESS, and a budget line that carries one without saying what it includes is the most common defect in early-stage storage capex.
Our published bands for 2026 separate three boundaries:
Equipment supply, ex-works INR 1.0–1.3 Cr per MWh
Installed CAPEX, utility-scale INR 1.3–1.8 Cr per MWh
Installed CAPEX, greenfield INR 1.6–2.3 Cr per MWh
The gap between the first line and the second is EPC: civil foundation, HV switchgear, power conversion, grid coupling and commissioning. It runs 25–40% on top of equipment supply, and it is not a small adjustment: the midpoints of the two bands are INR 1.15 Cr and INR 1.55 Cr per MWh, so on a 50 MWh programme the boundary alone is worth about INR 20 Cr.
Which line belongs in your budget depends on how you are contracting. If an EPC contractor holds the site works and you are buying equipment into their scope, the ex-works band is your line and the EPC's number is theirs. If you are contracting turnkey, the installed band is the line. Carrying the ex-works figure into a turnkey budget understates it by the whole 25–40% EPC adder, and that will not be discovered until bids arrive.
One more boundary worth naming explicitly: O&M is not capex. Annual operating cost for a utility-scale system runs INR 2–4 lakh per MWh per year. It belongs in the operating budget, and folding a year of it into the capital line to make a total look complete makes the per-MWh figure incomparable to every quote you will receive.
Contingency is a basis, not a percentage
The reflex is to take the middle of a band and add ten per cent. That is the wrong operation twice over: it treats a published range as a point estimate, and it adds a number with no derivation behind it.
The band is the contingency. For a utility-scale installed system the top of the published band is 38% above the bottom, and that spread is not noise — it is four identifiable drivers, each of which you can resolve for your own site before the budget is signed:
- Duration. A four-hour system lands near INR 1.8 Cr per MWh; a two-hour system near INR 1.3 Cr for the same power rating. Additional hours add cell cost close to linearly while the balance of system scales sub-linearly, so duration moves the per-MWh figure more than anything else on this list.
- Civil complexity. A greenfield site with no pad, no HV infrastructure and no connection point adds INR 0.25–0.5 Cr per MWh.
- Grid coupling voltage. An 11 kV or 33 kV interconnection with MV switchgear and transformer costs materially more than a low-voltage or behind-the-meter tie-in.
- Project size. Per-MWh EPC cost falls with scale. A 50 MWh project and a 5 MWh project are not the same unit cost.
Resolve those four and the band narrows considerably before you have spoken to a single supplier. What remains genuinely uncertain is commodity exposure, and that has its own basis: LFP cell prices move ±10–15% over a planning horizon, and cells are 52–55% of ex-works system cost. Propagated through, that is roughly 5–8% on the equipment line — a contingency figure you can show the derivation for, rather than a round number you cannot.
The lead time decides the financial year
This is the assumption that most often breaks a storage budget, and it breaks it in a way that is invisible until year-end.
Two different durations get called "lead time" and they are not interchangeable. Manufacturing lead time for containerised units is 14–18 weeks from a confirmed purchase order — that is the published figure for the BESS3000 to BESS10000 range, with cabinet products at 10–12 weeks. Project lead time for a utility-scale installation is 12–18 months, because it includes specification, tendering, financial closure, civil works, grid approvals and commissioning, of which manufacture is one block.
A budget line is committed when the purchase order is placed, but the cash typically moves against delivery and milestones. So work backwards from the in-service date, not forwards from the approval date:
Target in-service Q1 FY28-29 (Apr–Jun 2028)
Commissioning + grid approvals allow 8–12 weeks before that
Delivery to site 14–18 weeks before commissioning
Purchase order therefore Q3 FY27-28 at the latest
Run that backwards from an in-service date in the first quarter of FY27-28 instead and the purchase order has to be placed inside FY26-27 — which means the commitment, and often the advance, belongs to this year's budget rather than next year's. That is the single most common reason a storage line gets re-forecast: not that the number was wrong, but that the financial year was.
If the project is debt-funded, the same backwards walk has to accommodate financial closure, which has its own timetable. We covered the current structures in how Indian banks and DFIs are financing BESS projects; for budgeting purposes the point is that closure sits before the purchase order in the sequence, not beside it.
What to ask for at RFQ so the budget survives
A budget built on a published band is a planning figure. It becomes a defensible number the moment a real quote lands against it — but only if the quote is comparable to the assumption. Four things in the enquiry make that true.
State the basis of the capacity you are asking to be priced. DC nameplate and AC-deliverable differ by roughly 18% on a four-hour LFP system, which is larger than most of the site variables above. The arithmetic is in AC or DC? The 18% gap hiding in every BESS quote, and a budget priced against one basis and quoted against the other will not reconcile.
State the scope boundary you want priced, in the same words you used in the budget. Ex-works, delivered, or installed and commissioned.
Ask for a quote validity period. Cell commodity exposure is real, and a quote with no stated validity is a number that can move before the purchase order is raised. A validity window converts that exposure into something the contingency line can actually cover.
Ask for the warranty basis alongside the price. A five-year base cover and a twenty-year performance guarantee are different instruments with different costs, and a price quoted without saying which is included is not comparable across bidders. The wider structure is set out in our BESS procurement guide.
The short version
Put the installed band in the line if you are contracting turnkey and the ex-works band if you are not. Derive the contingency from the four drivers rather than adding a percentage. Then walk the schedule backwards from the in-service date, because the lead time is what decides which financial year the money belongs to.
The figures above are planning bands. For a sized configuration and an indicative capex against your own duration, site and grid coupling, talk to our team — we return a bill of quantities and a number within 48 hours of a specification-grade enquiry.